On 26 August 2026, the IRM registered a complaint, received on 23 August 2026, related to the implementation of GCF Project FP085 in Pakistan. The complainant(s) are members of Union Council-1, TMC Model Colony, Karachi, acting in their capacity as representatives and affected community members. The complainants have not requested confidentiality.

The complaint relates to GCF Project FP085, “Green BRT Karachi.” The project aims to build a zero emissions rapid bus transit system in the city of Karachi. Project activities include (i) construction of a bus rapid transport corridor of approximately 30 kilometers; (ii) operationalizing a biomethane hybrid bus fleet; (iii) flood proofing and improving transport corridors and (iv) construction of a biogas plant.

The complainants have brought to the IRM several concerns related to the implementation of the project. The complainants have alleged the following:

  • Destruction of water supply, gas and electric infrastructure due toconstruction works;
  • Improper disposal of construction debris, resulting in blockages tosewerage systems; and
  • Increased risk of flooding to roads due to construction activity;

As of 15 September 2026, the IRM determined the complaint to be eligible. 

Estado del caso

Abrir

23 Aug 2026

Elegibilidad / Investigación preliminar
Primeros pasos y elección del proceso
Cerrado

Políticas planteadas del GCF

Normas medioambientales y sociales
Política medioambiental y social

Documentación

Título Versiones
Carta de reclamación
Inglés
Determinación de la elegibilidad
Inglés

Detalles del proyecto

País Pakistán
Áreas de resultados
Transporte